Phase 2 Middle Bridge to Final Approach

Widening and removal of rocky intrusions may be difficult in places. Long haul for materials. Finishing this phase at middle bridge will allow the public to access phases 1&2 whilst work is in progress on phase 3.

Use contractors for prompt completion. Volunteers may be used for later installation of enhancements.

PlanPhase2.jpg (25184 bytes)

A     Widen as necessary, prepare ground, install drainage.

B     Install new path min. 2.4metres wide 500metres in length.

Forestry Division to supply timber for kerbs and rails.

Use contactors for ground-works and path.

 

(Back to top of page)

The Friends of the Glens - Isle of Man Registered Charity no. 928

Web hosted by Domicilium (IOM) Ltd, Domicilium House, 32-34 Malew St., Castletown, Isle of Man. IM9 1AE    www.domicilium.com

Copyright © 2005 Friends of the Glens
Last modified: April 25, 2006